Tasks Summary
Tasks Summary provides a quick and concise overview of Projected (Finish) Dates for all of the Tasks in the selected WorkPlan.
Tasks Summary Page
One row per Workplan Instance
Tasks picked as Columns
Each column has one Date per Task per Workplan.
Color coding on the cell is based on The statuses of Actual Finish Date, Projected Finish Date, the Current Date, and the N/A flag
Users may 'Pin' features by using the ellipsis menu
Filter by Task Date
Filtering by WorkPlan Task Dates (Baseline, Projected, Promised, Actual, Early, Late, and Configured Date Pairs) is available on the Filter Options.
Using Task Date Color Legend
The Projected Dates are color-coded for you to quickly and easily see the progression of the displayed WorkPlans. To see the Color Legend, click the ‘Task Date Color Legend’ Icon.
Task Color Legend Example
Exporting Task Details
You can easily export the data displayed in the rows of the Task Details Application Grid to a CSV file or directly to XLS by clicking the ‘Export’ Icon.
Showing Vizion Link Text of the Grid
You can show the Vizion Link (SQL) that was executed to pull the data for the grid by clicking the ‘Vizion Link’ Icon.
Editing WorkPlan Details
The "Info" button was added for the "WorkPlan Name" field. It opens the WorkPlan details form.