Tasks Summary provides a quick and concise overview of Projected (Finish) Dates for all of the Tasks in the selected WorkPlan.  




Tasks Summary Page


Tip
  • One row per Workplan Instance

  • Tasks picked as Columns

  • Each column has one Date per Task per Workplan.

  • Color coding on the cell is based on The statuses of Actual Finish Date, Projected Finish Date, the Current Date, and the N/A flag


Users may 'Pin' features by using the ellipsis menu


Filter by Task Date

Filtering by WorkPlan Task Dates (Baseline, Projected, Promised, Actual, Early, Late, and Configured Date Pairs) is available on the Filter Options.




Using Task Date Color Legend


The Projected Dates are color-coded for you to quickly and easily see the progression of the displayed WorkPlans.  To see the Color Legend, click the ‘Task Date Color Legend’ Icon.

 

Task Color Legend Example



Exporting Task Details

You can easily export the data displayed in the rows of the Task Details Application Grid to a CSV file or directly to XLS by clicking the ‘Export’ Icon.


Showing

SQL

Vizion Link Text of the Grid

You can show the Vizion Link (SQL) that was executed to pull the data for the grid by clicking the ‘Show SQL’ the ‘Vizion Link’ Icon.Image Removed

Image Added

 

Editing WorkPlan Details

The "Info" button was added for the "WorkPlan Name" field. It opens the WorkPlan details form.

HTML Comment

Updated 01/24/2022 Release 22.1.0 WP-176783

Updated 02/01/2021 Release 21.1 WP-117974

Updated 09/07/2020 Release 20.16 CodeQ-153687

Updated 05/11/2020 Release 20.8 Admin-157877

Updated 01/27/2020 Release 20.0 GUI Changes

Updated 09/10/2018 Release 8.91 Trackor-123411

Updated 6/25/2018 Release 8.85



On this Page

Table of Contents
maxLevel2